Urbanização Anadia

 

 

Inicio do Projecto: Wed 01-09-04

 

Fim do Projecto: Fri 11-03-05

Tarefas com Atribuições

ID

Task Name

Work

Duration

Start

Finish

% Work Complete

0

Urbanização Anadia

944,2 hrs

137,5 days

Wed 01-09-04

Fri 11-03-05

0%

1

INICIO (abertura de obra)

944,2 hrs

132,5 days

Wed 01-09-04

Fri 04-03-05

0%

2

Planeamento

72 hrs

25 days

Wed 01-09-04

Tue 05-10-04

0%

3

Contacto com cliente

8 hrs

1 day

Wed 01-09-04

Wed 01-09-04

0%

1

Cliente

8 hrs

 

Wed 01-09-04

Wed 01-09-04

0%

4

Realização e aprovação do projecto Técnico

64 hrs

24 days

Thu 02-09-04

Tue 05-10-04

0%

5

Contacto com gabinetes técnicos

0 hrs

1 day

Thu 02-09-04

Thu 02-09-04

0%

2

Gabinetes Técnicos

1

 

Thu 02-09-04

Thu 02-09-04

0%

6

Recepção de Propostas

48 hrs

6 days

Fri 03-09-04

Fri 10-09-04

0%

11

Sº Semião

48 hrs

 

Fri 03-09-04

Fri 10-09-04

0%

7

Escolha da Proposta mais favorável

8 hrs

1 day

Mon 13-09-04

Mon 13-09-04

0%

12

Direcção

8 hrs

 

Mon 13-09-04

Mon 13-09-04

0%

8

Apresentação do projecto ao cliente

8 hrs

1 day

Tue 14-09-04

Tue 14-09-04

0%

12

Direcção

8 hrs

 

Tue 14-09-04

Tue 14-09-04

0%

9

Elaboração do Projecto pela empresa escolhida, devidamente aprovado pela EDP

0 hrs

15 days

Wed 15-09-04

Tue 05-10-04

0%

2

Gabinetes Técnicos

1

 

Wed 15-09-04

Tue 05-10-04

0%

10

Adjudicação

0 hrs

2 days

Wed 15-09-04

Thu 16-09-04

0%

11

Aprovação dos materiais

104 hrs

14 days

Wed 06-10-04

Mon 25-10-04

0%

12

preparação da lista definitiva dos materiais

24 hrs

3 days

Wed 06-10-04

Fri 08-10-04

0%

13

Rui

24 hrs

 

Wed 06-10-04

Fri 08-10-04

0%

13

aprovação pelo dono de obra da lista dos materiais

0 hrs

1 day

Mon 11-10-04

Mon 11-10-04

0%

14

aprovação dos materiais pela EDP

80 hrs

10 days

Tue 12-10-04

Mon 25-10-04

0%

3

ARFARO

80 hrs

 

Tue 12-10-04

Mon 25-10-04

0%

15

Contacto com Fornecedores Habituais

64 hrs

6 days

Tue 26-10-04

Tue 02-11-04

0%

11

Sº Semião

48 hrs

 

Tue 26-10-04

Tue 02-11-04

0%

16

Orçamentação

0 hrs

4 days

Tue 26-10-04

Fri 29-10-04

0%

17

Nota de confirmação

16 hrs

2 days

Mon 01-11-04

Tue 02-11-04

0%

13

Rui

16 hrs

 

Mon 01-11-04

Tue 02-11-04

0%

18

Comprar material e equipamento

0 hrs

20 days

Tue 26-10-04

Mon 22-11-04

0%

19

Colunas, armaduras e base de betão das colunas

0 hrs

20 days

Tue 26-10-04

Mon 22-11-04

0%

4

ROLEAR

1

 

Tue 26-10-04

Mon 22-11-04

0%

20

Armários

0 hrs

15 days

Tue 26-10-04

Mon 15-11-04

0%

4

ROLEAR

1

 

Tue 26-10-04

Mon 15-11-04

0%

21

Cabos

0 hrs

5 days

Tue 26-10-04

Mon 01-11-04

0%

4

ROLEAR

1

 

Tue 26-10-04

Mon 01-11-04

0%

22

Preparar Obra

704,2 hrs

73,5 days

Tue 23-11-04

Fri 04-03-05

0%

23

Preparação do plano de trabalho

8 hrs

1 day

Tue 23-11-04

Tue 23-11-04

0%

6

Eng. Luís

8 hrs

 

Tue 23-11-04

Tue 23-11-04

0%

24

Início da obra

696,2 hrs

72,5 days

Wed 24-11-04

Fri 04-03-05

0%

25

Preparação do sítio

5 hrs

5 hrs

Wed 24-11-04

Wed 24-11-04

0%

5

Vários

5 hrs

 

Wed 24-11-04

Wed 24-11-04

0%

26

Sinalização das ruas

4 hrs

4 hrs

Wed 24-11-04

Wed 24-11-04

0%

5

Vários

4 hrs

 

Wed 24-11-04

Wed 24-11-04

0%

27

Piquetagens

20 hrs

1 day

Wed 24-11-04

Thu 25-11-04

0%

28

Piquetagem das valas

8 hrs

1 day

Wed 24-11-04

Thu 25-11-04

0%

6

Eng. Luís

8 hrs

 

Wed 24-11-04

Thu 25-11-04

0%

29

Piquetagem das colunas

4 hrs

0,5 days

Wed 24-11-04

Wed 24-11-04

0%

6

Eng. Luís

4 hrs

 

Wed 24-11-04

Wed 24-11-04

0%

30

Piquetagem dos armários

4 hrs

0,5 days

Wed 24-11-04

Wed 24-11-04

0%

6

Eng. Luís

4 hrs

 

Wed 24-11-04

Wed 24-11-04

0%

31

Piquetagem do PT

4 hrs

4 hrs

Wed 24-11-04

Wed 24-11-04

0%

6

Eng. Luís

4 hrs

 

Wed 24-11-04

Wed 24-11-04

0%

32

Valas

192 hrs

15 days

Thu 25-11-04

Thu 16-12-04

0%

33

Abertura de valas

120 hrs

15 days

Thu 25-11-04

Thu 16-12-04

0%

7

Pedreiros

120 hrs

 

Thu 25-11-04

Thu 16-12-04

0%

34

Colocação de Cabos

56 hrs

7 days

Thu 25-11-04

Mon 06-12-04

0%

8

Electricistas

56 hrs

 

Thu 25-11-04

Mon 06-12-04

0%

35

Enfiamento de cabos

16 hrs

2 days

Thu 25-11-04

Mon 29-11-04

0%

8

Electricistas

16 hrs

 

Thu 25-11-04

Mon 29-11-04

0%

36

Sinalização dos Cabos e Tapamento

0 hrs

5 days

Thu 25-11-04

Thu 02-12-04

0%

37

Armários

144 hrs

10 days

Thu 16-12-04

Thu 30-12-04

0%

38

Montagem dos armários

80 hrs

10 days

Thu 16-12-04

Thu 30-12-04

0%

8

Electricistas

80 hrs

 

Thu 16-12-04

Thu 30-12-04

0%

39

Eléctrodos de Terra

16 hrs

2 days

Thu 16-12-04

Mon 20-12-04

0%

8

Electricistas

16 hrs

 

Thu 16-12-04

Mon 20-12-04

0%

40

Ligações eléctricas

40 hrs

5 days

Thu 16-12-04

Thu 23-12-04

0%

8

Electricistas

40 hrs

 

Thu 16-12-04

Thu 23-12-04

0%

41

Limpeza

8 hrs

1 day

Thu 16-12-04

Fri 17-12-04

0%

5

Vários

8 hrs

 

Thu 16-12-04

Fri 17-12-04

0%

42

Colunas

136 hrs

12 days

Thu 30-12-04

Mon 17-01-05

0%

43

Instalação dos maciços de betão para fixar as colunas

0 hrs

6 days

Thu 30-12-04

Fri 07-01-05

0%

44

Montagem das colunas

96 hrs

12 days

Thu 30-12-04

Mon 17-01-05

0%

8

Electricistas

96 hrs

 

Thu 30-12-04

Mon 17-01-05

0%

45

Ligações eléctricas

40 hrs

5 days

Thu 30-12-04

Thu 06-01-05

0%

8

Electricistas

40 hrs

 

Thu 30-12-04

Thu 06-01-05

0%

46

PT

11,2 hrs

1 day

Mon 17-01-05

Tue 18-01-05

0%

47

Preparar o local do PT

0 hrs

1 day

Mon 17-01-05

Tue 18-01-05

0%

48

Colocar o PT no sitio indicado na Planta

3,2 hrs

0,5 days

Mon 17-01-05

Mon 17-01-05

0%

8

Electricistas

3,2 hrs

 

Mon 17-01-05

Mon 17-01-05

0%

49

Ligações eléctricas (BT/MT)

8 hrs

1 day

Mon 17-01-05

Tue 18-01-05

0%

8

Electricistas

8 hrs

 

Mon 17-01-05

Tue 18-01-05

0%

50

Obras prontas para vistoria

184 hrs

33 days

Tue 18-01-05

Fri 04-03-05

0%

51

Ensaios e Vistoria

8 hrs

1 day

Tue 18-01-05

Wed 19-01-05

0%

6

Eng. Luís

8 hrs

 

Tue 18-01-05

Wed 19-01-05

0%

52

Informar/ resposta EDP da vistoria

64 hrs

8 days

Wed 19-01-05

Mon 31-01-05

0%

6

Eng. Luís

64 hrs

 

Wed 19-01-05

Mon 31-01-05

0%

53

Vistoria pela EDP e ensaios

16 hrs

2 days

Mon 31-01-05

Wed 02-02-05

0%

9

Eng. da EDP

16 hrs

 

Mon 31-01-05

Wed 02-02-05

0%

54

Instalação técnica aprovada

0 hrs

10 days

Wed 02-02-05

Wed 16-02-05

0%

55

Informar/ resposta pela Câmara da vistoria

80 hrs

10 days

Wed 16-02-05

Wed 02-03-05

0%

6

Eng. Luís

80 hrs

 

Wed 16-02-05

Wed 02-03-05

0%

56

Aprovação da vistoria pela Câmara

16 hrs

2 days

Wed 02-03-05

Fri 04-03-05

0%

10

Eng. da Câmara

16 hrs

 

Wed 02-03-05

Fri 04-03-05

0%

57

Fim das obras e Início do período de garantia

0 hrs

0 days

Fri 04-03-05

Fri 04-03-05

0%

58

Inauguração

0 hrs

1 day

Thu 10-03-05

Fri 11-03-05

0%

 

1