Inicio do Projecto: Wed 01-09-04
|
Fim do Projecto: Fri 11-03-05 |
![]() |
|
ID |
|
Work |
Duration |
Start |
Finish |
% Work Complete |
|
0 |
Urbanização Anadia |
944,2 hrs |
137,5 days |
Wed 01-09-04 |
Fri 11-03-05 |
0% |
|
1 |
INICIO (abertura de obra) |
944,2 hrs |
132,5 days |
Wed 01-09-04 |
Fri 04-03-05 |
0% |
|
2 |
Planeamento |
72 hrs |
25 days |
Wed 01-09-04 |
Tue 05-10-04 |
0% |
|
3 |
Contacto com cliente |
8 hrs |
1 day |
Wed 01-09-04 |
Wed 01-09-04 |
0% |
|
1 |
Cliente |
8 hrs |
|
Wed 01-09-04 |
Wed 01-09-04 |
0% |
|
4 |
Realização e aprovação do projecto Técnico |
64 hrs |
24 days |
Thu 02-09-04 |
Tue 05-10-04 |
0% |
|
5 |
Contacto com gabinetes técnicos |
0 hrs |
1 day |
Thu 02-09-04 |
Thu 02-09-04 |
0% |
|
2 |
Gabinetes Técnicos |
1 |
|
Thu 02-09-04 |
Thu 02-09-04 |
0% |
|
6 |
Recepção de Propostas |
48 hrs |
6 days |
Fri 03-09-04 |
Fri 10-09-04 |
0% |
|
11 |
Sº Semião |
48 hrs |
|
Fri 03-09-04 |
Fri 10-09-04 |
0% |
|
7 |
Escolha da Proposta mais favorável |
8 hrs |
1 day |
Mon 13-09-04 |
Mon 13-09-04 |
0% |
|
12 |
Direcção |
8 hrs |
|
Mon 13-09-04 |
Mon 13-09-04 |
0% |
|
8 |
Apresentação do projecto ao cliente |
8 hrs |
1 day |
Tue 14-09-04 |
Tue 14-09-04 |
0% |
|
12 |
Direcção |
8 hrs |
|
Tue 14-09-04 |
Tue 14-09-04 |
0% |
|
9 |
Elaboração do Projecto pela empresa escolhida, devidamente aprovado pela EDP |
0 hrs |
15 days |
Wed 15-09-04 |
Tue 05-10-04 |
0% |
|
2 |
Gabinetes Técnicos |
1 |
|
Wed 15-09-04 |
Tue 05-10-04 |
0% |
|
10 |
Adjudicação |
0 hrs |
2 days |
Wed 15-09-04 |
Thu 16-09-04 |
0% |
|
11 |
Aprovação dos materiais |
104 hrs |
14 days |
Wed 06-10-04 |
Mon 25-10-04 |
0% |
|
12 |
preparação da lista definitiva dos materiais |
24 hrs |
3 days |
Wed 06-10-04 |
Fri 08-10-04 |
0% |
|
13 |
Rui |
24 hrs |
|
Wed 06-10-04 |
Fri 08-10-04 |
0% |
|
13 |
aprovação pelo dono de obra da lista dos materiais |
0 hrs |
1 day |
Mon 11-10-04 |
Mon 11-10-04 |
0% |
|
14 |
aprovação dos materiais pela EDP |
80 hrs |
10 days |
Tue 12-10-04 |
Mon 25-10-04 |
0% |
|
3 |
ARFARO |
80 hrs |
|
Tue 12-10-04 |
Mon 25-10-04 |
0% |
|
15 |
Contacto com Fornecedores Habituais |
64 hrs |
6 days |
Tue 26-10-04 |
Tue 02-11-04 |
0% |
|
11 |
Sº Semião |
48 hrs |
|
Tue 26-10-04 |
Tue 02-11-04 |
0% |
|
16 |
Orçamentação |
0 hrs |
4 days |
Tue 26-10-04 |
Fri 29-10-04 |
0% |
|
17 |
Nota de confirmação |
16 hrs |
2 days |
Mon 01-11-04 |
Tue 02-11-04 |
0% |
|
13 |
Rui |
16 hrs |
|
Mon 01-11-04 |
Tue 02-11-04 |
0% |
|
18 |
Comprar material e equipamento |
0 hrs |
20 days |
Tue 26-10-04 |
Mon 22-11-04 |
0% |
|
19 |
Colunas, armaduras e base de betão das colunas |
0 hrs |
20 days |
Tue 26-10-04 |
Mon 22-11-04 |
0% |
|
4 |
ROLEAR |
1 |
|
Tue 26-10-04 |
Mon 22-11-04 |
0% |
|
20 |
Armários |
0 hrs |
15 days |
Tue 26-10-04 |
Mon 15-11-04 |
0% |
|
4 |
ROLEAR |
1 |
|
Tue 26-10-04 |
Mon 15-11-04 |
0% |
|
21 |
Cabos |
0 hrs |
5 days |
Tue 26-10-04 |
Mon 01-11-04 |
0% |
|
4 |
ROLEAR |
1 |
|
Tue 26-10-04 |
Mon 01-11-04 |
0% |
|
22 |
Preparar Obra |
704,2 hrs |
73,5 days |
Tue 23-11-04 |
Fri 04-03-05 |
0% |
|
23 |
Preparação do plano de trabalho |
8 hrs |
1 day |
Tue 23-11-04 |
Tue 23-11-04 |
0% |
|
6 |
Eng. Luís |
8 hrs |
|
Tue 23-11-04 |
Tue 23-11-04 |
0% |
|
24 |
Início da obra |
696,2 hrs |
72,5 days |
Wed 24-11-04 |
Fri 04-03-05 |
0% |
|
25 |
Preparação do sítio |
5 hrs |
5 hrs |
Wed 24-11-04 |
Wed 24-11-04 |
0% |
|
5 |
Vários |
5 hrs |
|
Wed 24-11-04 |
Wed 24-11-04 |
0% |
|
26 |
Sinalização das ruas |
4 hrs |
4 hrs |
Wed 24-11-04 |
Wed 24-11-04 |
0% |
|
5 |
Vários |
4 hrs |
|
Wed 24-11-04 |
Wed 24-11-04 |
0% |
|
27 |
Piquetagens |
20 hrs |
1 day |
Wed 24-11-04 |
Thu 25-11-04 |
0% |
|
28 |
Piquetagem das valas |
8 hrs |
1 day |
Wed 24-11-04 |
Thu 25-11-04 |
0% |
|
6 |
Eng. Luís |
8 hrs |
|
Wed 24-11-04 |
Thu 25-11-04 |
0% |
|
29 |
Piquetagem das colunas |
4 hrs |
0,5 days |
Wed 24-11-04 |
Wed 24-11-04 |
0% |
|
6 |
Eng. Luís |
4 hrs |
|
Wed 24-11-04 |
Wed 24-11-04 |
0% |
|
30 |
Piquetagem dos armários |
4 hrs |
0,5 days |
Wed 24-11-04 |
Wed 24-11-04 |
0% |
|
6 |
Eng. Luís |
4 hrs |
|
Wed 24-11-04 |
Wed 24-11-04 |
0% |
|
31 |
Piquetagem do PT |
4 hrs |
4 hrs |
Wed 24-11-04 |
Wed 24-11-04 |
0% |
|
6 |
Eng. Luís |
4 hrs |
|
Wed 24-11-04 |
Wed 24-11-04 |
0% |
|
32 |
Valas |
192 hrs |
15 days |
Thu 25-11-04 |
Thu 16-12-04 |
0% |
|
33 |
Abertura de valas |
120 hrs |
15 days |
Thu 25-11-04 |
Thu 16-12-04 |
0% |
|
7 |
Pedreiros |
120 hrs |
|
Thu 25-11-04 |
Thu 16-12-04 |
0% |
|
34 |
Colocação de Cabos |
56 hrs |
7 days |
Thu 25-11-04 |
Mon 06-12-04 |
0% |
|
8 |
Electricistas |
56 hrs |
|
Thu 25-11-04 |
Mon 06-12-04 |
0% |
|
35 |
Enfiamento de cabos |
16 hrs |
2 days |
Thu 25-11-04 |
Mon 29-11-04 |
0% |
|
8 |
Electricistas |
16 hrs |
|
Thu 25-11-04 |
Mon 29-11-04 |
0% |
|
36 |
Sinalização dos Cabos e Tapamento |
0 hrs |
5 days |
Thu 25-11-04 |
Thu 02-12-04 |
0% |
|
37 |
Armários |
144 hrs |
10 days |
Thu 16-12-04 |
Thu 30-12-04 |
0% |
|
38 |
Montagem dos armários |
80 hrs |
10 days |
Thu 16-12-04 |
Thu 30-12-04 |
0% |
|
8 |
Electricistas |
80 hrs |
|
Thu 16-12-04 |
Thu 30-12-04 |
0% |
|
39 |
Eléctrodos de Terra |
16 hrs |
2 days |
Thu 16-12-04 |
Mon 20-12-04 |
0% |
|
8 |
Electricistas |
16 hrs |
|
Thu 16-12-04 |
Mon 20-12-04 |
0% |
|
40 |
Ligações eléctricas |
40 hrs |
5 days |
Thu 16-12-04 |
Thu 23-12-04 |
0% |
|
8 |
Electricistas |
40 hrs |
|
Thu 16-12-04 |
Thu 23-12-04 |
0% |
|
41 |
Limpeza |
8 hrs |
1 day |
Thu 16-12-04 |
Fri 17-12-04 |
0% |
|
5 |
Vários |
8 hrs |
|
Thu 16-12-04 |
Fri 17-12-04 |
0% |
|
42 |
Colunas |
136 hrs |
12 days |
Thu 30-12-04 |
Mon 17-01-05 |
0% |
|
43 |
Instalação dos maciços de betão para fixar as colunas |
0 hrs |
6 days |
Thu 30-12-04 |
Fri 07-01-05 |
0% |
|
44 |
Montagem das colunas |
96 hrs |
12 days |
Thu 30-12-04 |
Mon 17-01-05 |
0% |
|
8 |
Electricistas |
96 hrs |
|
Thu 30-12-04 |
Mon 17-01-05 |
0% |
|
45 |
Ligações eléctricas |
40 hrs |
5 days |
Thu 30-12-04 |
Thu 06-01-05 |
0% |
|
8 |
Electricistas |
40 hrs |
|
Thu 30-12-04 |
Thu 06-01-05 |
0% |
|
46 |
PT |
11,2 hrs |
1 day |
Mon 17-01-05 |
Tue 18-01-05 |
0% |
|
47 |
Preparar o local do PT |
0 hrs |
1 day |
Mon 17-01-05 |
Tue 18-01-05 |
0% |
|
48 |
Colocar o PT no sitio indicado na Planta |
3,2 hrs |
0,5 days |
Mon 17-01-05 |
Mon 17-01-05 |
0% |
|
8 |
Electricistas |
3,2 hrs |
|
Mon 17-01-05 |
Mon 17-01-05 |
0% |
|
49 |
Ligações eléctricas (BT/MT) |
8 hrs |
1 day |
Mon 17-01-05 |
Tue 18-01-05 |
0% |
|
8 |
Electricistas |
8 hrs |
|
Mon 17-01-05 |
Tue 18-01-05 |
0% |
|
50 |
Obras prontas para vistoria |
184 hrs |
33 days |
Tue 18-01-05 |
Fri 04-03-05 |
0% |
|
51 |
Ensaios e Vistoria |
8 hrs |
1 day |
Tue 18-01-05 |
Wed 19-01-05 |
0% |
|
6 |
Eng. Luís |
8 hrs |
|
Tue 18-01-05 |
Wed 19-01-05 |
0% |
|
52 |
Informar/ resposta EDP da vistoria |
64 hrs |
8 days |
Wed 19-01-05 |
Mon 31-01-05 |
0% |
|
6 |
Eng. Luís |
64 hrs |
|
Wed 19-01-05 |
Mon 31-01-05 |
0% |
|
53 |
Vistoria pela EDP e ensaios |
16 hrs |
2 days |
Mon 31-01-05 |
Wed 02-02-05 |
0% |
|
9 |
Eng. da EDP |
16 hrs |
|
Mon 31-01-05 |
Wed 02-02-05 |
0% |
|
54 |
Instalação técnica aprovada |
0 hrs |
10 days |
Wed 02-02-05 |
Wed 16-02-05 |
0% |
|
55 |
Informar/ resposta pela Câmara da vistoria |
80 hrs |
10 days |
Wed 16-02-05 |
Wed 02-03-05 |
0% |
|
6 |
Eng. Luís |
80 hrs |
|
Wed 16-02-05 |
Wed 02-03-05 |
0% |
|
56 |
Aprovação da vistoria pela Câmara |
16 hrs |
2 days |
Wed 02-03-05 |
Fri 04-03-05 |
0% |
|
10 |
Eng. da Câmara |
16 hrs |
|
Wed 02-03-05 |
Fri 04-03-05 |
0% |
|
57 |
Fim das obras e Início do período de garantia |
0 hrs |
0 days |
Fri 04-03-05 |
Fri 04-03-05 |
0% |
|
58 |
Inauguração |
0 hrs |
1 day |
Thu 10-03-05 |
Fri 11-03-05 |
0% |